Hello,

In quiz "Project stages and statuses", the correct answer to question #2 " Moving a project to a different Kanban stage affects its status." is "False", but when I move a project from one column to another, its status changes to "In Progress". What did I get wrong?

Best regards, Chris

아바타
취소
베스트 답변

This would be True only if you have grouped the Projects by Status.

If you move 'AGR - S00066 - Sales Order' to another kanban Stage in above scenario, the Status will actually change - because the Stage actually reflects the Status.

A more obvious example would be to group Projects by Project Manager. Moving 'Renovation' from Stage 'Mark Demo' to 'Mitchell Admin' in below example will actually set the Project Manager to 'Mitchell Admin'. But - nothing else.


The question you are talking about specifically refers to Project Stages - as a dedicated 'Stage Stage': https://youtu.be/8yzslSQbg-s?t=60, thus changing the '(Project) Stage' Stage does not affect the Status:

아바타
취소
작성자

Thank you for your very clear answer, Christoph. I definitely need to learn more about the ins and outs of Odoo...