Why does Odoo split RFQ's made by MTO and made when I run a scheduler?

Products set up with MTO will created an RFQ when they are sold (Vendor is X)
when I run the scheduler to check the stock (based on reordering rules) and reorder when needed an new RFQ is created (vendor is also X).

I want them to be on 1 RFQ>

I saw that an MTO is added to an open RFQ. Run scheduler will always created a new PO

Avatar
Discard
Best Answer

Check the propagation option 


The system if the RQF for the same vendor has option to merge it or create new on controling using propagation option 

Active Devloler mode and multi steps routes 

Buy route then rule the propagation options 