Hi,

When re-ordering rules create new manufacturing orders, the MOs reserve raw materials as soon as they are generated. I would like that the MOs doest not reserve raw materials, as when one creates a MO manually. Is there an option or config anywhere to set this parameter ?

Thanks

Avatar
Discard
Best Answer

While manually created MOs are in draft stage, the MOs created with rules are defaulted to confirm stage. Please do refer the post below, hope it helps in validating relevance to your case and framing a solution.

https://www.odoo.com/forum/help-1/can-i-modify-mps-to-create-draft-state-manufacturing-orders-184244