Hi,

when I create a MO, I must always set a future "scheduled date", because all RfQs and MO/WO are created backward from that date. This works fine so far.

but if I create a SO, today's date is taken for the MO and thus all RfQs etc. are dated back! how can I avoid this, so a product sold today will start all calculations from today onward, or a product to be delivered in 6 month is scheduled accordingly?

regards, Tilli

Avatar
Discard
Author Best Answer

while I found an explanation in the docs "calculation of lead times" (//doc.openerp.com/5.0/it/book/5/5_15_Manufacturing/5_15_Manufacturing_lead/) I still believe the system should not just schedule thinks into the past.