Hi,

How do I change the quantity of items to consume on the production order ?

For example I have an article 1 X  = 4 a + 10 b
To make Article 10 of X there must be consumed 40 a + 100 b is the parameter level nomenclature of Article X
But the actual production of gold Article X I need to consume 50 a + 100 b to produce 10 X

 

Avatar
Descartar
Best Answer

You verify Bill of Materials and value Manufacturing Efficiency, this value, for you, should be 1.0.

Avatar
Descartar
Autor Best Answer

Thank you for your reply

But for our case I do not have the same data for all production orders.

It means that sometimes I used 50 a has produced 10 article X, sometimes +, sometimes -

For each production, I do not know in advance the exact quantities required.