HI ,

I AM USING STANDARD COSTING METHOD AND I HAVE A PLAN CHANGE TO AVCO . IS IT MAKE ANY ISSUE FOR MY PRESENT STOCK OR ACCOUNTING ? LOOKING FOR YOUR MOST VALUABLE FEEDBACK . THANK YOU

Avatar
Descartar
Best Answer

I think: The existing standard cost will be starting point for average cost calculation. The first goods receipt will calculate new average cost. 

Good pratice: Test and documet in a copy of production database before doing changes like that. 