Currently
in Odoo, we can setup 2 step picking for receipts, delivery, and manufacturing,
but not for the subcontracting route.
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- إدارة علاقات العملاء
- e-Commerce
- المحاسبة
- المخزون
- PoS
- Project
- MRP
لقد تم الإبلاغ عن هذا السؤال
1. Activate the
subcontracting route on the Manufacturing module.
2. Go to the Inventory module > Configuration > Operation Type
3. Create a new operation, with the type Internal Transfer, and set the source location to be the picking location, and destination location to be the output location:
4. Go to the Inventory module >
Configuration > Routes > Resupply Subcontractor
5. Change the current rule to the
following configuration:
6. Create a new rule with the following
configuration:
Make sure to set the two rules on the following order:
Now, when the user creates the PO for the trigger the
subcontracting process, there will be a picking operation before the delivery:
هل أعجبك النقاش؟ لا تكن مستمعاً فقط. شاركنا!
أنشئ حساباً اليوم لتستمتع بالخصائص الحصرية، وتفاعل مع مجتمعنا الرائع!
تسجيلالمنشورات ذات الصلة | الردود | أدوات العرض | النشاط | |
---|---|---|---|---|
|
1
يونيو 21
|
3116 | ||
|
3
مارس 25
|
19042 | ||
|
2
مايو 21
|
9339 | ||
|
1
فبراير 22
|
3677 | ||
|
1
أغسطس 24
|
3867 |