How can I create an automated action that changes the color of a task if the task remains in a certain stage for a certain time?

For example: I have a project called "project" with three stages "New", "In Progress", "Done". I have a task called "task" in that project. Now I want the color of the task to be changed into red when the task is in the stage "In Progress" for more than a week.

الصورة الرمزية
إهمال
أفضل إجابة

Yes, I have seen this being done at a functional training. Make you action write on the color field. The code for the red colour is 2.

Also interesting for an Automated Actions is the kanban_state field, that shows as a green or red light in the Kanban view cards. Change it to blocked when you're near to the deadline to get the red light in the issue or task.

الصورة الرمزية
إهمال
المنشورات ذات الصلة الردود أدوات العرض النشاط
1
يناير 17
10668
3
أبريل 24
2058
1
سبتمبر 23
1939
1
مايو 23
1962
1
ديسمبر 23
4657