تخطي للذهاب إلى المحتوى
القائمة
لقد تم الإبلاغ عن هذا السؤال
2 الردود
2866 أدوات العرض

I've created a task, which is composed from a few subtasks. So when tracking the effective time of subtasks it does not relate to the parent task. Basically what I would expect was to see the progress of the task - the sum of the effective time of the subtasks.

Did anyone experienced the same issue when tracking time on tasks? Thank you.

الصورة الرمزية
إهمال
أفضل إجابة

Good morning,

On the list view, I would like to track the Initial planned time, the hours spent and the remaining ones, but in the case of tasks + subtasks, the remaining time is not treated as I expected.

Is more easy to understand with an example. I have a parent task with 2 subtasks, the time traking looks as follows:

||Task name||Initialy planned||Hours Spent||Hours Spent subtasks||Total||Remaining||
|Task         |00:00|00:00|57:30|57:30|-57:30|
|Subtask 1|06:00|06:00|00:00|06:00|00:00|
|Subtask 2|30:00|51:30|00:00|51:30|-21:30|
|                 |36:00|57:30|         |          |-79:00|


The Remaining column takes into accont the Total of hours instead of the Hours Spent. 

Then, the sum of the remaining column is not correct, beacuse it aggregates the spent hours on tasks + subtasks. Following the example, I expect 0:00 for the 'Remaining' on the parent task and  -21:30 for the total of remaining time.

How can I manage that to really reflect the time spent on subtasks and the real remaining time?

We are using Odoo v15, community edition

Thanks

الصورة الرمزية
إهمال
أفضل إجابة

Hi Daniil,

Which specific task view are you referring to?

On the Task list view and pivot view you can add columns 'Hours Spent' which is specific to task, 'Sub-tasks hours spent' which is time recorded in the sub-tasks and then 'Total Hours' which is the total for a task & sub-tasks

The progress bar on the list view & task timesheet tab includes time on task + sub task. The initially planned hours on the main task is (task hours + sub task hours ) if left blank the progress bar doesn't show as effectively it is -ve on task

Thanks and regards

الصورة الرمزية
إهمال
المنشورات ذات الصلة الردود أدوات العرض النشاط
0
يونيو 23
1368
0
ديسمبر 24
452
0
سبتمبر 24
471
0
مايو 24
276
1
نوفمبر 21
2017