I am trying to create a Stockable Product, Procurement Methd: Make to Order, Supply Method: Manufacture. I have created orderpoint Minimum=30 Maximum=0

Bill of Materials for this products contains another two products which has 0 Minumum and 0 Maximum Orderpoint.

When I Confirm Sales Order and Run Scheduler, I have Two Request for quote for the all items in Bill Of Materials.

I thought we should have only one request for quote for each item in Bill Of material. Can some one help me to understand?

Appreciate.

Thanks

形象
丢弃
最佳答案

make_to_order /never/ looks at available stock. You have the first RFQ because the procurement for this product was set to make_to_order, so it literally created an order. You have the second RFQ because the scheduler noticed the orderpoint and created a RFQ for it.

To do what you probably want to do, set your product to make_to_stock. This will hit 'exception' because there is no inventory, and then the scheduler will check the orderpoint, notice < 30 stock, and create one RFQ for 40 (30 keep in stock + 10 you needed)

形象
丢弃
编写者

Thanks CB. I will verify the flow as per your suggestion and post my feedback. Thank you once again.