Hey everyone, 

via the chatter my users create activities (mail.activity) model. Users can mark the activities as completed in the chatter as normal. Now I have the problem that if the user wants to display the open activities via the clock symbol, then entries with already completed (state=done) activities are also displayed in the list. Unfortunately, this becomes very confusing for the user.


I suspect that I have inadvertently removed a filter at some point. I only used odoo studio for the customizations.


Any hints on which action or in which view must the filter be set again? 


Thanks for your help and best regards

Joshua

形象
丢弃
编写者 最佳答案

In Activity Types" menu and after selecting the desired activity the "Keep Done" option was set. This is what caused the error.

https://www.odoo.com/de_DE/forum/hilfe-1/how-to-keep-activities-alive-after-marking-them-as-done-246782


形象
丢弃
相关帖文 回复 查看 活动
1
10月 23
1714
1
6月 25
352
1
2月 25
861
0
2月 25
1012
1
10月 24
1120