Hey everyone, 

via the chatter my users create activities (mail.activity) model. Users can mark the activities as completed in the chatter as normal. Now I have the problem that if the user wants to display the open activities via the clock symbol, then entries with already completed (state=done) activities are also displayed in the list. Unfortunately, this becomes very confusing for the user.


I suspect that I have inadvertently removed a filter at some point. I only used odoo studio for the customizations.


Any hints on which action or in which view must the filter be set again? 


Thanks for your help and best regards

Joshua

Avatar
Descartar
Autor Mejor respuesta

In Activity Types" menu and after selecting the desired activity the "Keep Done" option was set. This is what caused the error.

https://www.odoo.com/de_DE/forum/hilfe-1/how-to-keep-activities-alive-after-marking-them-as-done-246782


Avatar
Descartar
Publicaciones relacionadas Respuestas Vistas Actividad
1
oct 23
1679
1
jun 25
325
1
feb 25
842
0
feb 25
996
1
oct 24
1097