Hi,

We have multiple projects with the same stages. But in Kanban view e.g. "My tasks" the "To Do" stage shows up per project.

It looks like they are grouped by stage ID. How can I get them grouped by stage name instead?

Thanks in advance,
Jörn

Avatar
Vazgeç

Thanks a lot! That clarified it.

Is there a way to define stages added to every new project?

En İyi Yanıt

Instead, if you want to share common stages among projects then follow the steps,

- Create stages

- Create projects

- again, go to stages form view (with developer mode) and assign list of projects.