This question has been flagged
1 Cevapla
1478 Görünümler

Hello, I need to restrict tasks access in the project application. For example: I created a new project and created 5 subtasks and I assigned them to different users. What I need is to allow each user to see only his assigned tasks no more. Is there a way to do it?

Avatar
Vazgeç
Best Answer

Hello,

1. you can achive that by Going to project setting -> edit -> set visibility to "invited employees"


2. Now -> create new task -> set assignees to "test" employee for example:

note : test user will be allowed to see only tasks that assigned to him/her by going to "My Task" menu item, also when he/she opens "Projects" menu item -> will not see the project itself



Hope this will help.