Hi all, I have this use case and Im on Odoo 18: 

I'm in the reception area and I've just received a PO, I have to complete a pending internal transfer:

  • WH/STOR/00004
  • Operation type: Almacen Central: Storage
  • Source: WH/Input/Dock A
  • To: WH/Stock
  • Product: Test Product
  • Units: 2500

What is the correct way to split the 2500 units into 5 pallets before completing the Internal Transfer?


Thanks in advance.



Awatar
Odrzuć
Najlepsza odpowiedź

On the product line, click the hamburger icon to specify quantities and select the destination package (pallet name) to split into individual pallets prior to validating the transfer.