I have a BOM with following 

FP 5 KG = (Row Material 1, Row Material 2)

I have a Routing has three WC (Preping, Cooking, Testing)

In Preping all raw materials will be used as per the BOM to produce 5 KG FP

In Cooking no Row Material will consume but what we get with preping Operation, will be cooked which is 5 KG.

Note: After done with Cooking we got 4KG instead of 5. (its not scrping )

So when it goes to next work center Testing, odoo takes operation of 5 QTY, But actully after cooking we have 4QTY as we loose 1kg during the cooking.

How can we fit this scenario in Odoo13 ?

Is there any app is available to fit this or any other references ?

Thank you!

Awatar
Odrzuć
Najlepsza odpowiedź

Hi,

If it Possible try this app. 

​https://apps.odoo.com/apps/modules/12.0/mapol_mrp_plan_order
https://apps.odoo.com/apps/modules/12.0/mapol_check_mrp_product_quantity_12

Awatar
Odrzuć
Powiązane posty Odpowiedzi Widoki Czynność
3
kwi 25
3731
3
cze 21
3538
2
sty 24
20245
5
sty 24
12046
1
lut 21
3295