Skip to Content
Menu
Musisz się zarejestrować, aby móc wchodzić w interakcje z tą społecznością.
To pytanie dostało ostrzeżenie
1 Odpowiedz
1465 Widoki

Hello , i have a situation 

we buy product X and Y, and i want to transform them both into Z after the purchase 

(my boss wants it this way to keep easy track on stock disponibilities


so how should i do this ? is it by setting a route or else ? what i want is as soon as X or Y are purchased , an MO is automatically created to transfrom it to Z 


is this possible . thank you very much for your help 

Awatar
Odrzuć
Najlepsza odpowiedź

You need to have requirement for Product Z.  You can create that with Reordering rules for product Z.  Use Min / max  qty and rounding.  Product Z must have route Manufacturing. And of course a BOM where you use product X and Y as components. 

If you set the reodering rule to automatic the scheduler action will create manufacturing orders when stoc for product Z is below min qty.  You can also set the reordering rule to manual and use the menu Operation -> Replenishment to create manufacturing orders.  Will appear as soon as qty in staock is below min qty.

Manufacturing orders must be confirmed

But: From what you write it seems like you manager want to register the components as finished products, without actually doing it. If that is tha case telle you manager: Never ever transform product in the system unless you also do it physically.  Your stock figures should always be accurate to what you actully can go and count.  This is the only way to control your business correct. (I tell this for 30 years as logistic manager.)  There are other tools to know how much you have the possibility to deliver.

Awatar
Odrzuć
Powiązane posty Odpowiedzi Widoki Czynność
2
maj 25
911
1
sie 24
3344
2
lip 25
489
2
sty 23
1950
3
gru 21
6858