We use product tracking with expiration dates for purchased products, everything set up, including Expiration Time etc of products.

BUT: Expiration Date is calculated upon RFQ/PO Confirmation Date (purchase.order.date_approve), which is useless for POs, and not on Receipt Effective Date (stock.picking.date_done) which is what we need and expect. Alternatively

I would appreciate any advice how to fix this issue, preferably with settings or Studio. If this needs coding, well then please give more details :-)

Thanks

Awatar
Odrzuć
Najlepsza odpowiedź

Hi,

Just had a look at runbot 16.0 and checked out git branch 16.0, expiration date is compute based on the receipt date.

Regards!

Awatar
Odrzuć
Autor

Hi Jason,
thanks for your effort. Looks like within customization someone screw it up. Has been put back to standard now