Hi,

Is there a way to check how many employees working/assigned in specific project?

I checked the Personal module but couldn't find a link between employee profile and a Project.

Note: I'm not asking user accesses. Just workers related with Projects.

Avatar
Descartar
Best Answer

From project reporting pivot view you can group by project followed by assignees, this would provide the employees working on a project. You can set the measure to count, planned, remaining hours etc