Sometimes project.task throw a notification with subtype "Stage changed" but sometimes not? is this normal?

Where in workflow a change the stage throw a notification with "Stage changed" subtypes?

Avatar
Descartar
Best Answer

Yes it is.

The notification "Stage changed" is only sent if the new state is not new, done or open.

Here is the related code snipped in the source code:

'stage_id': {
    'project.mt_task_stage': lambda self, cr, uid, obj, ctx=None: obj['state'] not in ['new', 'done', 'open'],
Avatar
Descartar
Autor

thanks for your answer but if I switch between 2 stages that have the same state(in progress for example) no notification is throw.