Hello,
We are trying to record our project timesheet costs totals for each month on the balance sheet - which is proper accounting method. Projects can span multiple months and we need a way to recognise the value of timesheet costs accurately on the balance sheet at the end of the month - without generating a customer invoice.
Does anyone know how to handle this?
If I could trouble you once again, would you mind helping me understand if any additional steps are required when the final invoice is paid? Here is a scenario: we have a single project and book x hours in April and then, using this method, we put it on the balance sheet/PL on 31/4/23. Then, we book y hours on the project and also add that to the balance sheet/PL. Once the job is done, and the invoice is sent out, are we likely to double up here?
I have some more feedback from the team:
To clarify, our bookeeper/accounts is looking to record labour on the Balance Sheet in a WIP account as tasks are undertaken, and then move those labour costs to the P&L as tasks are invoiced. We are using Manufacturing and Field Service modules.
The transaction flow is:
Payroll postings are debited to a Labour Expense Account
As chargeable field services work is undertaken, this same expense account is credited for any labour costs, with a corresponding debit to WIP on the Balance Sheet.
As field services work is invoiced, the WIP accounts is credited, with a corresponding debit to COGs on the P&L
Using an analytic account we can filter on transactions for the month to produce a monthly journal entry to move labour from the expense account to the WIP account. However, we can not find a way to identify the sum of labour costs associated with field services tasks that have been invoiced for the month.
We also undertakes some manufacturing, and here we have the opposite problem. When hours are recorded against work orders, Odoo automatically credits the WIP account with the full cost, including labour, upon completion of the work order. We have an separate account set on the Virtual Location/Production. However, we can not identify the sum of labour costs to debit to the WIP account for work that was undertaken (whether or not the products were completed).