Hello;

We are evaluating the projects module in Odoo but we have a problem: we can only assign time to the task but this is not enough since we need to assign materials too and monitor the actual usage. Every project management tool assign: time, materials and expenses to tasks.

Are we missing something? Or this feature is not available?

Regards,

Emad

Avatar
Descartar
Autor Best Answer

Hello Kasongo,

Thank you. Can we track expenses at the task level or is it just at the project level?

Regards,

Avatar
Descartar
Best Answer

Hi Emad,

Materials on project's tasks is unfortunately a missing feature at the time of this answer. However you can perfectly track all expenses of the related project and re-invoice them to your customers.

Regards,