Hi ! I use Cost Structure in MRP, it's very usefull. But I would like to know if it's possible to calculate the total time and price for producing a product (Sum of all workcenters of subpoducts in my BOM, and that recursively).

Somebody has an idea?

Thx.

John

Avatar
Descartar
Best Answer

If you configure cost per hour account on your workcenter it will count the costing of your production of finish product which will generate analytic entries..

Regards, Mustufa Rangwala