I am phasing some issues to track the unused metal sheet from the Manufacturing process

ex. I have a metal sheet standard size which is an 8x4 foot sheet in size dimension while purchasing from a vendor and I want to keep that metal sheet in Unit as Purchase UoM 

and in one of the finished products BoM, I want to use 2x2 foot of metal pieces from the 8x4 foot, after using the 2x2 foot in the MRP how should I track the remaining 3/4th of the metal sheet in inventory and reuse that remaining sheet which can be used for other MRP

Kindly help me out for the solution 

Avatar
Descartar
Best Answer


If you are using a 2x2 foot piece from a 8x4 foot sheet, the correct consumption factor would be:

Consumption Factor=Area of Used SheetArea of Full Sheet=2×28×4=432=18Consumption Factor=Area of Full SheetArea of Used Sheet​=8×42×2​=324​=81​

So, the correct consumption factor is 1/8​, not 1/4

Avatar
Descartar
Autor Best Answer

Hello bro I have just shared an example scenario and thank you for the calculation part but could you please elaborate on the feasibility of Odoo working on my query? I need to track the remaining piece of sheet and reuse it for the next MRP and not Purchase a new one.

Avatar
Descartar
Best Answer

You would need to track using lot numbers, assign a lot for each sheet and on consumption the remaining qty can be identified.

Hope your UoM is set in sq feet

Avatar
Descartar
Related Posts Respostes Vistes Activitat
1
de maig 22
2238
1
de maig 22
5300
0
de març 22
2679
1
de juny 17
5069
1
de jul. 24
4268