Hi,

When I produce a good through subcontracting or manufaturing based on a bill of material including a service with an associated cost, I only have the component cost taken into account. Why?

Thank you for your time,

Avatar
Descartar
Best Answer

Service product don't work in manufacturing. But Product with tracing (non stock product) should work.  Try that.