When we are making an internal transfer from A to B, If B requests some amount of products from A via internal picking requisitions, and after B receives the request B will do the Transfer. The transferred quantity will directly go to A's warehouse stock location without notifying A. Is there any possibility of putting a GRN point for A to check the received quantity before adding it to the stock location?

Avatar
Descartar
Best Answer

Inventory->Settings->Operations and mark the Reception Report here. I think this is what you are looking for.