Hello,

do you know why the operations tab in BOM form is not display?

Is there is something to set ?

Vincent

形象
丢弃
最佳答案

Hi,

Did you enabled Work Order's feature from manufacturing settings ? If not, activate it from settings, the operation page will get visible in the bill of materials.


Thanks

形象
丢弃
编写者 最佳答案

Hi Mehjabin,


Thank you for your answer but it was not the problem here.

i found the problem, it was because my user was not in the group mrp.group_mrp_routings

形象
丢弃

Yes, the work order boolean in mrp settings is linked with this user group

编写者

Ok Mehjabin, i didn't know that.
So your answer was the good one.
Thank you again !