Does any one know why the gantt view shows projects with a duration set as estimated time divided per 3 ? This is not related to the number of person in the team nor the Working time"

形象
丢弃
最佳答案

I believe this is the bug reported in Launchpad as "[7.0/Trunk] WorkOrder end dates not correct when changing dates on Gantt view" (cannot add the link due to low karma).

Seems no fix is available as of now...