I am trying to find the origin of the problems about my MRP schedulers.
Some of the Production orders are not generated during standard run. I usually have to run schedulers manually. After 30-40 minutes of manual run those missing manufacturing orders are created.

[I have mrp_jit installed, mrp schedulers set to run every 50 mins]

Question is: How can I find the log file for JIT scheduler or how can I enable logging for MRP schedulers ?