In V16 there is the Delivery Status in Sales, which is very useful. What irritates me a little: Sometimes “Fully Delivered” is highlighted in red, sometimes in green. Is there a reason for this?

形象
丢弃
最佳答案

Delivery Status also considers WHEN products were delivered.

It compares the delivery date promised with the last ACTUAL delivery date.


You can look at the XML definition of the List View to understand:

Fully Delivered is GREY when

  • all products are delivered
  • no date was promised to the Customer

Fully Delivered is GREEN when

  • all products are delivered
  • all deliveries were made on or before the date promised

Fully Delivered is RED when

  • all products are delivered
  • not all deliveries were made on or before the data promised


RED basically means LATE.

形象
丢弃
最佳答案

gray means delivered on time

形象
丢弃
编写者

sorry, maybe I'm stupid: what is the difference to green? Ray wrote: green: "all deliveries made on..the date promised"

编写者 最佳答案

Thanks Ray, that's helpful. Last question: what means "light gray"?

形象
丢弃

Please see my updated answer.
Also, when you ANSWER a post, only OP is notified [if different from the person posting the answer].
It was pure chance I saw this question.
In the future, to notify someone you have a follow-up question, comment on the reply.