Hi, recently discovering Odoo Project. (using the online web based version only)

I have created tasks only containing a deadline date. Is it possible to change the task and add a begin and end date to a taks so it will appear in the Gantt view? Or do I have to recreate these tasks from scratch from the Gantt view?

Thanks in advance for your answer!

Br. Erwin

形象
丢弃
最佳答案

hello, I think it depends of you odoo version (community or enterprise). In enterprise, when using gant view and adding task you have planned date: