Can we reschedule the Start and End Date of the Sub Tasks automatically if the Parent Task get reschduled?

Imagine profil
Abandonează
Cel mai bun răspuns

Yes, this is possible in many project management software applications. In Microsoft Project for example, if the parent task is rescheduled, the subtasks will automatically adjust to reflect the new dates. Some other software applications may have an option to turn this feature off, so it is best to check the application's help documentation.

Imagine profil
Abandonează
Autor Cel mai bun răspuns

Hi Kamlesh Ind.

In Odoo default you need to manually change the Date of the Sub Tasks.

But we are having a custom module Gantt View Project, in this you can link tasks of a project to one another.

We have given tasks to be scheduled in two ways "Auto" and "Manual", in Manual mode you have to shift tasks manually for both linked and independent tasks. But if the linked or dependent tasks will be in auto mode and if you will reschedule/move/change the main task date then the linked tasks will be automatically rescheduled.

In Odoo Gantt View App, Auto-schedule automatically schedules a dependent task easily by just linking it with a main task. Relocating the main task schedule in the Gantt View will result in the linked task getting auto-scheduled based on the end date of the main task. The latter starts automatically as the main task ends.

If you need any assistance or support, please don't hesitate to reach out. Our team is always here to help!"

Regards,

Ksolves Team!

Imagine profil
Abandonează
Related Posts Răspunsuri Vizualizări Activitate
0
mai 24
276
1
sept. 20
2626
0
mar. 15
3300
0
mar. 15
3658
1
feb. 21
2256