HEllo

The module project_timesheet states that it: "This module lets you transfer the entries under tasks defined for Project Management to the Timesheet line entries for particular date and particular user with the effect of creating, editing and deleting either ways"

So if I have some time declared in a task within a day D and then create a timesheet over a week containing the day D, I should expect to see the amount of time declared in the task, also appearing in the timesheet.

This does not happen => How can we wynchronise the time declared on tasks with the timed eclared within timesheets ?

Thank you

Franck

Imagine profil
Abandonează
Cel mai bun răspuns

Hello Franck,


Actually changes in the tasks summary are automatically reflected in the Human Resources timesheet. Steps to verify that:

1. Encode a work summary on a task and save

2. Go to Human resources > Time Tracking > My Current Timesheet and click on the "Detail" tab of your timesheet. You should find the recently encoded timesheet

3. Alternatively you can go to Human resources > Time Tracking > My Timesheet activities.

Imagine profil
Abandonează
Related Posts Răspunsuri Vizualizări Activitate
1
iul. 18
3793
1
mar. 15
5916
1
mar. 25
1393
0
mar. 25
1181
0
apr. 21
4217