We are using version 10. 

Is there any way to change the routing for manufacturing order after the "Workorder" is created? 

More description:

I have a product (computer desk) with two bills of material (BoM), and each bill of material has different routing (with some different operations)

When we create a sale order, a new manufacturing order is created automatically.

After we create workorder base on the BoM and routing, is there any way to change routing or BoM?


Imagine profil
Abandonează
Cel mai bun răspuns

It is not possible you should plan it first before you start the production and you can use PLM to plan these changes

PLM

Versioning

Easily get differences between versions to track changes.

PLM

Track versions of products and ECO's as well as their respective documents. Merge different ECO's corresponding to the same BoM.

Engineering Changes

Track changes with a great kanban process for ECOs.

Document Management

Store plans and worksheet directly on bill of materials and routings.


Imagine profil
Abandonează
Autor Cel mai bun răspuns

Thanks for the reply.

I understand it is not possible from the UI of the application. But I was wondering if it is possible programmatically? Is there an Odoo's programmers forum I can post this in?

Imagine profil
Abandonează
Related Posts Răspunsuri Vizualizări Activitate
2
ian. 20
2872
6
oct. 18
5934
2
dec. 24
8675
0
mar. 23
1829
1
mai 22
5420