How to restrict the simultaneous manufacturing operations in odoo 14?

I would like to start my second process only after the completion of first process.

in v14 i can start the process concurrently.

how to restrict this?

Imagine profil
Abandonează
Cel mai bun răspuns

Hello,

In odoo manufacturing there is no option for run the work order in sequence. In BoM you can manage the sequence of work order but its not strictly follow in manufacturing order. 

For your requirement you have to do some changes in existing odoo flow.