What is the best way to adjust for consumed components on a closed Manufacturing Order so that the cost analysis and inventory both get adjusted?

Example: The manufacturing order was closed however is was discovered that one of the components was reporting as 28 units consumed when in reality only 7 where used in the product. 

An entry can be done to put the 21 units back into inventory with an inventory adjustment however the cost of the Production order would not reflect this. I am looking for a way to correct both the inventory as well as the costing of the order.

Imagine profil
Abandonează
Autor Cel mai bun răspuns

I just figured this out. 

From the production order if you unlock and edit you can select the product and adjust the "Done" quantity. After you save on the pop up screen you have to hit save on the Production Order as well and then the Cost as well as the product stock moves get updated accordingly. 