Hi, Using versione 7, how to set planned time for the projects (project managemen module)?

Thank you

Portretas
Atmesti
Best Answer
  1. Go to Settings / Configuration / Project and check Manage time estimation on tasks then -> Apply.
  2. In task form now it should be field Initially Planned Hours.