Hi,

When clicking in the Proyect menu, the default view is kanban, I would like to know how to change it to be the tree view by default

Thanks in advance

Portretas
Atmesti
Best Answer

HI,

You can change the default view mode using project_view.xml file of project module:

<field name="view_id" ref=" view_project "></field>  <!-- For Tree View -->

instead of

<field name="view_id" ref="view_project_kanban"/>

OR:

Edit the action(Settings/Technical/Actions/Window Actions) with name: Projects and give tree view reference of project.project.tree in View Ref.

Portretas
Atmesti
Autorius

thanks, it worked

Best Answer

Thank you. It helps me too.

Portretas
Atmesti
Best Answer

Take a look at:

https://www.openerp.com/apps/7.0/product_tree_view_by_default/

https://www.openerp.com/apps/7.0/partner_tree_view_by_default/

These modules do the same thing for products and partners.