Ir al contenido
Menú
Se marcó esta pregunta

Was looking to utilize the new specific capacities function of work centers.   


It seems to only work for scheduling?  I was hoping it would also be used for calculating cost from the BOM.  

I can't seem to get it to abide by different setup and cleanup times.  Has anyone utilized this yet?

Avatar
Descartar

For what I haved used the specific capacities, you are right. It works mostly for scheduling, and it a llows you to indicate specific setup and clean up times for the products you indicate in the BoM.

https://www.cybrosys.com/odoo/odoo-books/odoo-book-v16/manufacturing/work-centers/#:~:text=The%20Specific%20Capacities%20tab%20can,specified%20in%20the%20Capacity%20field.

Publicaciones relacionadas Respuestas Vistas Actividad
1
jul 25
315
2
feb 24
2576
2
dic 23
1495
0
nov 23
977
1
mar 15
4870