I'm having the following issue with Odoo 8 PMIS module:
When accessing Project > Tasks and selecting the Gantt view, I can't see the end date, they only appear on creation date until today and I can't set end date manually if it's posterior to today date.

Screenshot: https://i.stack.imgur.com/mHq6k.png

Did someone have a similar issue about it? Thanks.