Can someone explain the use of ROUTING, and what is the use of NUMBER OF CYCLES and NUMBER OF HOURS?? and how is it related to WORK CENTER OPERATION?? Please any suggestions/comments would be appreciated.. THANKS
 

Avatar
Opusti
Best Answer

If production process includes several operations then ROUTING define in wich sequence process move through their.

If for production process on WORK CENTER need repeat operation several times then you define NUMBER OF CYCLES.

For calculate production time you need define forecast time of execution of each operation as NUMBER OF HOURS.

All it need for planning purpose.

Avatar
Opusti
Avtor

thanks Mr Vasiliy Birukov..