Hello, I have make a server action who create a crm.meeting object at the creation of a project.task.work object. I want to have a single calendar with all "meetings"(holidays, meeting, project task and so on).

But work object has just a duration and a date field, how can I calculate the date_deadline field for meeting object with one datetime and one float.

I remember that for duration 8:30=8,5 in database.

I don't know how to do.

Avatar
Opusti
Best Answer

Maybe you could use the datetime and timedelta Python module if you are programming it?

Avatar
Opusti
Avtor

I'll test it

Avtor

thanks a lot

Best Answer

Dear, seee the lunch module ...

Avatar
Opusti
Avtor

what can I found on lunch module?

You will find a way to add days to the current date in demo data XML file!

Best Answer

try this:

<field name="date_deadline" widget="float_time"/>

Avatar
Opusti
Avtor

error:" arch: Invalid XML for View Architecture!' ". But thanks for help. I will try to build a function who make this and call it in my view.

'date_deadline' must be of type float btw. I have a payroll system that uses that function specially for the biometric and attendance