I have created the reordering rules and also i have marked the buy, and make to order ticks in the product profile. And have added a vendor too in the vendor tab of the product profile. Still PO is not generating when a SO is confirmed. I even ran the scheduler, but no luck.

頭像
捨棄

Lukshala - I have a similar case where we are a trading company and depending on price and availability we can buy from any supplier at any given time and not necessarily if Qty = 0 then PO is generated (for exports usually delivery times are 3-4 weeks and stock is available ex-stock).

Have you found a way to pull individual line items from the SO into 1 PO? And then a few other line items in another PO?

最佳答案

Hi Lukshala,

The scheduler will create an RFQ. You will need to confirm the RFQ to convert it into a PO.

頭像
捨棄

Not creating even the RFQ