Hi all,

I'm trying out the v7 and so far everything has worked and it was easy. The only problem I have is Sign in / Sign out by project.

I guess I don't really understand how that works. I have created a few projects with tasks. When I do a "manual" time sheet entry with HR/My Current Timesheet or with projects task "Work summary" time sheet gets populated.

I would like to use "HR/Sign in / Sign out by project" so that I don't have to track time spent on a project/task manually. Unfortunately every time I try to use it, the "Project / Analytic Account" field contains only "Create and Edit".

On the demo database I can select some products but still can't select the newly created project.

I'm doing something wrong but I don't get what? I searched the manual, forum and this site and I can't find anything relevant to this issue.

Can someone shed some light on how to use this feature?

Thanks Dragan

Avatar
Vazgeç

Anything on this? Having the same issue.

Same issue .... with the nighty version (17/02/2014).

which version ?

Version 7.0-20140217-002618

En İyi Yanıt

After some investigation, It seems that the "sign in and sign out by project" functionality supports only normal analytic account.... There are 4 different types of accounts (Analytic view, Analytic Account, Contract or project, template of contract) For my point of view it is a bug! Do you know if anybody created a bug report on launchpad about that topic ?

I've just created (22/02/2014) a bug report on launchpad [1283446] and I also post a possible solution.

Avatar
Vazgeç

Any updates?

İlgili Gönderiler Cevaplar Görünümler Aktivite
1
Tem 18
3812
1
Mar 25
1426
0
Mar 25
1194
0
Nis 21
4237
1
Kas 19
3006