Hello everyone,
I am new to Odoo.

At the moment, I am trying to create manufacturing orders.


For the duration of the manufacturing order, 
I can only select the "start" of the planned date, but then I can not see / select "end" of the planned date (which I want to manually control the duration of the order)


The only way I can change the duration of the order is when I click into "Planning by workcentre", then select the order, go into "Time tracking", then manually select the new range of "Planned date".

I hope my question make sense.


Thank you for your help.


Kind Regards,

Edward