Hello all,

I see Odoo 14 allows work orders to run in parallel with one another. But one of our customers requires to stop running in parallel and it should run in sequence (e.g, Second work order should be started only when the first work order is completed). 

How do i Make this happen in Odoo 14?


Thanks,

Odoo @tenthPlanet


Avatar
Abbandona

You're talking about work orders within one manufacturing order, right? Presumably you have no problem with workorders running in parallel for different MOs, right?