Hi friends,

The progress bar works fine on form view for project.project showing correct value of work done on a project, but when i add the same field to kanban view via xpath, it does not update value of prgress bar field, it shows empty progress bar.Any suggestion..................[Odoo 8.0 Project] .

Avatar
Buang
Jawaban Terbai

Try widget="guage" in xml