Hi,

I'm working with PMIS module and I got a different view from what I was expecting of Gantt chart on Project > Tasks. I might be misunderstanding something, but could ye help me figuring it out?


I got it right when I click Project > Portfolio > Work Packages:

http://imgur.com/a/08O5k


But I got this when I click Project > Tasks:

http://imgur.com/a/ra8eM

It does not show the deadline, the starting and ending date. And getting P0.D1 as an example, I do have a deadline for that:

http://imgur.com/a/WWnIr


So what I am missing? Or am I using it wrongly?