Hi all,

Thanks to the authors of the Manufacturing requirements list, good job.

Only few remarks

Product
-------------
Missing feature: products could have a revison/version. A product revision have a matching plan/drawing revision
impact in sale/purchase order line, stock move, etc. Really used in sub contractor industry

Product Category
------------------------------------
As it's defined "Specify Quality Control lines". That's ok but quality control lines are like
standard routing lines of operations made in a workcenter. Then maybe ok to attach defaut routing to product category

BOM
----------
"Have many BOM Versions but only one active at a specific date" OK but depends sometimes of subcontractor availability or internal ressource availability

Work center / Operation
----------------------------------------
"Define a Supplier if the operation is subcontracted": In general buyers (and planification service) in industry want to choose/change subcontractor by themselves (price or availability). They only want than manufacturing services define what kind of skills is needed for the operation

Factory
-----------
off topic (sorry @maxime)
physical machine -> workcenter -> workshop -> plant/factory
For each you need to define most of the same informations and have an easy structure to calculate (time charging)
May be we could consider it like a chart of accounts or product categories


Thanks for the intiative


my 2 cents



David BEAL - Akretion - Odoo Development / Integration
+33 (0)6 67 22 86 89 - +33 (0)4 82 53 84 60


2014-09-04 14:04 GMT+02:00 Maxime Chambreuil <maxime.chambreuil@savoirfairelinux.com>:
Good morning everyone,

The target version has not been decided yet.

First we want/need to define what the user will be able to do. User doesn't care about the version at this point, the same about how features are split/architectured in terms of modules.

Priority is defined at requirement #3, set on product, partners, etc. at #6, #9 #13 and #28 and used at #106, #107 and #146.

Regards,
--
Maxime Chambreuil
+1 (514) 276-5468 #126


Thanks a lot to everyone involved.
Has it been agreed already which version will be the target, v7 or v8?
Lionel.

_______________________________________________


_______________________________________________
Mailing-List: https://www.odoo.com/groups/community-59
Post to: mailto:community@mail.odoo.com
Unsubscribe: https://www.odoo.com/groups?unsubscribe