by
Bista Solutions US, Ray Carnes
- 11/17/2015 15:48:18

I had to have RFQ merging written for v9 – it is no longer available.


Ray.

 

From: Arjan Duijs [mailto:arjanduijs@gmail.com]
Sent: Tuesday, November 17, 2015 8:18 AM
To: Community <community@mail.odoo.com>
Subject: Re: implementation questions MPR / purchase

 

I forgot to mention, we are using a odoo v9 out of the box.

So as for the merging POs, this seems to be different from v8, but no documentation on how

 

2015-11-17 9:36 GMT-05:00 Arjan Duijs <arjanduijs@gmail.com>:

Hi all,

I have some questions about the implementation of the manufactoring and the purchases modules .

Would like to know how you guy are dealing with certain situations and the implementation of that withing odoo.

 

Our current (non-odoo) process/situation is that a work order is generated when a sale is closed.

This work order contains ALL the items that need to be manufactored.

- Within odoo this generates a bunch of work orders, one for each type of item.

 

Since we can have a quite extensive list of various items for a customer/project 30-40 different workorders looks a bit overwhelming. (or is this normal?)

 

A similar situation with the purchases,

We dont dispatch purchase orders every day to providers but we like to collect a reasonable amount before ordering (for reduced transportation costs) or simply because we only place orders on a fixed day of the week.

 

So after a bunch of sales orders there can be quite some pending purchase orders (20+) for a single provider. 

Is there a way to combine them all to a single PO? 

 

like to know how you guys are handling these situations

 

thanks

 

 

 